Week 13 - Brick and Framing

Image
A lot happened this week that is pretty visible. See below, by area. The brick walls on the sides if the yard were finished. It's all really coming together now. Look at that beautiful wall! And there's one on the other side, too! Closer view of the west garden wall. The end of the wall will tooth into the back (north) wall of the back yard. Not quite sure why there aren't spaces to tooth in at the top here...there's a brick wall all along the back, too. On to the interior! I walked in the front door and was surprised by what I saw... They moved the door! This actually makes a lot of sense. As you can see here on the right, they started framing in the door opening to turn it into the pass-through window. The door actually locks now vs. it being held in place with an angled 2x4 before. This is the main wall (back wall) of the kitchen, along the east side. You can see the new plumbing piping. The one at the left is connecting to t...

Week 11 & 12 - Ductwork, Framing, & Some Demo

Image
I mean to post this two weekends ago and then the week  and weekend got away from me. Here's an update from the past couple of weeks. The weather week before last was cold, rainy, or both, so most of the work happened inside. It was mechanical rough-in week! Ductwork in the addtion Supply duct Vertical riser from the basement Other Supply duct Basement end of the vertical supply duct End of the basement duct that connects to the furnace and feeds the main room. Main room ductwork Ductwork in main room along east wall Ductwork in main room along east wall Ductowork looking to the mechanical spaces, along the basement east wall Basement closet supply Basement bathroom supply Wall at the mech room/storage closet New register in the twins' room. New register in Saha's room. I had a site visit with the contractor, plumber, and electrican this past Wednesday to go over the plumbing and electrical rough...