The past week the contractor has been busy pouring concrete. Last week I shared the formwork, but this week, there's more!
|
A week ago Thursday, we had a crazy rainstorm, so Friday morning, there was a foot of water in the hole. It didn't rain that much but I think that our whole roof and our neighbor's drained into the hole. Took the contractor a couple of hours to pump it out. |
|
This is what was under all that water, a concrete footer! Hooray! |
|
A closer in shot of the footer |
By Wednesday, we had concrete foundation walls!
Next week, they finish the concrete and then continue work on the addition. In the next couple of weeks we should have brick walls.
We are about a month in, received our first pay request, and things appear to be on schedule. It will go a lot faster once the concrete is completely done.