Week 18 - Drywall Finishing

Last week there was a lot of finishing work done. The roof on the addition was installed along with the skylights, and the windows were installed.

Our new windows are in!


The dryer and bathroom vent pipes

New standing seam metal roof and skylights - view from the twins' room.


View from Saha's room
Moving back down, some images of the living room and kitchen.


Looking from the living room through to the addition. 

See all that great north-facing light from the addition?!

The North wall of the kitchen. The pass-through window is behind that plywood



Looking back toward the living room.


New vent opening in the floor that will feed through the bottom of a cabinet.

New windows from the inside.


The view the next day (when the contractor's weren't there) So much great light.



The pass-through window and where the new banquette seating will be.


Looking down to the mudroom landing

Our new, code-compliant electrical panel, that's NOT in the bathroom!

Basement bathroom.

The basement shower.

Basement playroom/family room/guest room. Looks almost the same as before but a nice rectangle.


Looking back toward the addition from the family room.

The mechanical room and our new furnace.
Next post will have a few more exciting things! Stay tuned. Just 3-4 more weeks to go until we're back in the house.